Home / Executive programme health assessment

Battlehill Projects

Executive programme health assessment

Give a sponsor an evidence-based view of delivery confidence and the decisions required.

Illustrative example · Fictional scenario · Not a customer document

Illustrative enterprise-system implementation approaching UAT. The example distinguishes reported progress from the evidence required to support release confidence.

AreaAssessmentEvidence / gapRequired action
Integrated planAmberPartner milestones exist; business data preparation is not on the critical path.Programme manager to reconcile the dependency plan before approving the baseline.
Business acceptanceRedUAT scenarios do not cover two priority operating processes.Business owner to approve complete scenarios before test entry.
Service readinessAmberSupport ownership is identified; knowledge-transfer evidence is incomplete.Service lead to agree acceptance evidence and handover dates.
Financial controlGreenForecast and approved scope reconcile in this fictional example.Continue monthly review and assess proposed changes.

The decision this helps you make

Sponsor decision: hold the release commitment until UAT coverage and the integrated baseline have been reviewed. Confirm the owners and dates for closing the evidence gaps.